Temporary access and construction plans developed, general contractor selection underway
December 2021
Project nearing final design
Permit applications to appropriate agencies submitted
Construction to begin after permitting approved
Construction to last up to three years
Construction activities that could temporarily disrupt vessel traffic will be directed by the U.S. Coast Guard and U.S. Army Corps of Engineers, to be communicated to the maritime community early and often
BNSF to provide timely and consistent updates and outreach to affected stakeholders and neighboring communities
October 2020
BNSF crews repair steel tower supports on the south side of the bridge
Work occurs over four weeks, most occurring between 9 a.m. and 2 p.m.